Take a seat, stay for the view!
Moffat Beach locals and visitors will soon enjoy easier access to one of the Sunshine Coast's most loved beaches, with key areas of the foreshore set to reopen in time for the September school holidays.

The Moffat Beach seawall reconstruction project has reached several major milestones, with the rock seawall nearing completion, with only minor adjustment works and the construction access track still to be built, and work progressing into the final stages.
The project is restoring and strengthening a vital stretch of coastline while protecting community assets, public infrastructure and the much-loved foreshore from future severe weather and coastal impacts.
Council is working closely with contractors, local businesses and the community to deliver the project as efficiently as possible while minimising disruption.

Sunshine Coast Division 2 Councillor Terry Landsberg said the team had made significant progress over recent months, despite challenging weather, tidal and ocean conditions.
"We know the community and local businesses are looking forward to seeing more of Moffat Beach reopen, and we're pleased to be working towards reopening the eastern car park and improving access to the foreshore ahead of the September school holidays," Cr Landsberg said.
Beach clean-up activities are underway and construction areas will be progressively removed as works are completed, allowing more of the beachfront to be returned to public use.
"We're now moving from the heavy construction phase into the finishing stages of the project," Cr Landsberg said.
"Over the coming weeks, the construction footprint will continue to shrink and the foreshore will begin to look and feel more like the Moffat Beach everyone knows and loves."
Eastern beach bar
Another recent milestone is the completion of the new eastern beach bar, providing a fantastic new vantage point to take in the sweeping coastal views.
Whether it's enjoying a morning coffee, watching the surfers or simply soaking up the sea breeze, the beach bar is already becoming a popular place to pause and enjoy the scenery.

Western foreshore and fence
Cr Landsberg said Council had listened to community feedback about the western foreshore area and, following a detailed assessment of options, had decided to replace the fence with a second concrete ground slab with a single height sandstone wall that matches the existing stone wall along the eastern section of the foreshore.
The seawall reconstruction remains the immediate focus, with the western foreshore improvements planned to start after the September school holidays and take up to one month, with a smaller construction footprint.
The project is expected to be fully completed and all remaining construction infrastructure removed by the end of October, weather and ocean conditions permitting.

Moffat Beach is open!
The beach, cafés and shops are open and ready to welcome you.
If parking is limited, consider riding your bike, walking or catching public transport. With 50-cent fares, getting to Moffat Beach has never been easier.
"Thank you for your patience and support as we deliver a stronger, safer and more resilient foreshore for Moffat Beach," Cr Landsberg said.
"The end is in sight, and we look forward to welcoming our community back to more of the foreshore in the coming months."
For more information and project updates, visit Council's Moffat Beach Seawall Reconstruction Project webpage.
The Moffat Beach Seawall Reconstruction Project is funded by Sunshine Coast Council, the Australian and Queensland governments through the jointly funded Commonwealth-state Disaster Recovery Funding Arrangements (DRFA) and the Queensland’s Department of Transport and Main Roads.